Procurement

No sub-line created on the PO when selecting Replenishment Delivery on the Claim
Issue When creating a manual Claim (PPS390 Return To Supplier) and selecting the Replenishment Delivery option why is the sub-line not creating on the PO f...
Wed, 8 Sep, 2021 at 6:42 AM
99 Status in Purchase Order net order value
Issue Why is the PO line total (LNAM) with a Status 99 still accounted for in the net order value (NTAM) ?  Resolution That is standard M3 functi...
Wed, 22 Dec, 2021 at 1:01 PM
Standard price is zero | Procurement
Issue Getting an error message - 'WARNING - Standard price is zero' when placing a Purchase Order for a new item.     A standard cost has be...
Fri, 28 Jan, 2022 at 6:28 AM
PO has no charges calculation
Issue The PO Header / Line charges does not have any calculations. Resolution There are no values in the costing elements were those items meet the c...
Thu, 2 Jun, 2022 at 11:29 AM
Supplier Return - Manually Created
Purpose How to create a claim to the supplier for faulty or rejected items. Before you start  Stock must be isolated in a location with status balance I...
Mon, 20 Jun, 2022 at 1:22 PM
Need more information on the Carrier Departure date in PPS270
Purpose of the field Impact on the Material plan how is calculated Purpose of the field The purpose of Carrier departure date is to tra...
Wed, 5 Jun, 2024 at 1:39 PM